Thursday, March 17, 2016

Local Government Engineering Department (LGED) Information

Growth Center Markets, Union Parishad Complex Bhabans, Server Station for Electoral Database Project, Hydraulic Structures for Irrigationpurpose, Road & Bridge/Culvert etc. are implementing by different projectsof LGED at this Pabna district.

List of few project’s name is given below:
  1. Second Rural Transport Improvement Project (RTIP-II)
  2. Priority basis Rural Road & Hat/Bazar Infrastructure Development Project (Infra)
  3. Important Rural Infrastructure Development Project on Priority Basis
  4. Bhangura – Nowgaon GCM Road Development Project.
  5. Construction of Housing for Landless & Under Provileged Muktijoddhas Project
  6. Construction of Upazila Muktijuddho Complex Bhaban
  7. Improvement of Rural Roads, bridge/culvert & other Infrastructure of Backward Upazilas (Pabna, Sirajgonj, Natore, Naogaon, Rajshahi, Nawabgonj & Bogra Districts) of Northern-Western Region.
  8. Primary Education Development Project (PEDP-3)
  9. Primary Education Development Project (IDB)
  10. Participatory Small Scale Water Resources Sector Project
List of few important on going scheme’s name is given below:
  1. Improvement of (a) Mathurapur UP - DB Gram UP road Ch: 0+110Km - 1+058Km & 2+908Km - 4+486Km Length=2.523Km  (b) Maligasa UP office - Ramchandrapur RHD road Ch: 0+000km - 0+330km, 2+130km - 4+139km, 4+455km - 5+480km & 5+980km - 8+880km Length=6.264km.
  2. Construction of 211.74m Long RCC Girder bridge on Bhangura – Noagaon GCM road at Ch: 4025m
  3. Construction of 211.74m Long RCC Girder bridge on Bhangura – Noagaon GCM road at Ch: 2700m.
  4. Construction of 211.74m Long RCC Girder bridge on Bhangura – Noagaon GCM road at Ch: 10860m
  5. Construction of 120.00m Long RCC Girder bridge on Bhangura – Noagaon GCM road at Ch: 6860m.
  6. Improvement of Bhangura – Noagaon GCM road at Ch: 8950m – 9650.
  7. Construction of Upazila Muktijuddho Complex  Bhaban at Chatmohar Upazila.
  8. Construction of Upazila Muktijhodhha Complex Bhaban at Faridpur  Upazila.
  9. Construction of Upazila Muktijuddho Complex  Bhaban at Bera Upazila.
  10. Construction of Remaining work of 160.10m PC Girder Bridge on Noagaon road at Ch: 600m over Gomani River at Nowbaria Ghat.

No comments: